Rakhine State

Kyauk Phyu Deep Sea Port Project

Kyauk Phyu Tanker Port Project

Location

-

Made Island, Kyauk Phyu Township, Rakhine State

Type of Cargo

-

Tanker port

Start Date of Construction

-

31-10-2009

Implementing Parties

-

Ministry of Energy and South East Asia Pipeline Company-CNPC are being taken Joint-Venture.

Preliminary work Progress

-

Construction of Work Boat Wharf and revetment, Leveling of project area Construction of relevant building and preparations for Tanker Project.

Accommodative size of vessel

-
-
-
-

LOA-300 meters
Width of Beam-60 meters
Draft-26 meters
DWT-30000

Expect Completion Date

-

31-9-2013

 

Implemented Work Boat Wharf at Made Island, Kyauk Phyu

Rakhine State

Kaladan Multi-Modal Transit Transport Project

Description: http://localhost:8080/mpa.gov.mm/images/stories/wharf27.jpgDescription: http://localhost:8080/mpa.gov.mm/images/stories/wharf28.jpg

 

 

 

 

 

 

 

Location                                     -     Along the Kaladan River from Sittwe Port to Mizoran, India is 1294 Km.

Objective                                    -     To facilitate the cargo transport to Mizoran through Rakhine State and border of Myanmar-India

Date and venue of Signing agreement -        2-4-2008, Newdaily, India

Establishment of Working Committee   -        13-8-2009

Project Period                             -     4 yrs

Project execution                        -     Development of Sittwe Port and Kaladan River , allocation of navigation aids along the Kaladan River from Sittwe to Paletwa and construction of road link from Palatwa to India-Myanmar border.

Project Cost                                -     US$ 117.38 Millions

Progress of pre-engineering works -     Hydrographic survey for navigation Channel and Sittwe harbor.

 

 

Construction of road link from Palatwa to India-Myanmar border

Length of road link    -     Palatwa to India-Myanmar border 248 Kilometers (154 miles)